Our participation in the Maya Train project
Plant 1. Balzapote, Veracruz: The main objective of this project is the production of ballast, as well as gravel and sand in the same crushing process; this material will be used subsequently in civil works. The main supply of production is the Maya Train.
The project consists of a primary and secondary crushing plant with an independent dedusting system to remove clays, yielding a 100% crushed fine product of excellent quality. Additionally, we integrated conveyor belts for a production capacity of 150 TPH.
Plant 2. Cancún, Quintana Roo: We are currently working on the optimization of a second plant for this project, which is likely aimed at producing 100% crushed sands and gravel, for a production of 250 TPH, with FIMSA equipment and the client’s own equipment.